True or False?An activity with a high certainty of risk combined with a high consequence of impact must never be actioned.
Question
True or False?
An activity with a high certainty of risk combined with a high consequence of impact must never be actioned.
Solution
This statement is False. While it is true that activities with both a high certainty of risk and high consequences can be dangerous, it is not accurate to say that they must never be actioned.
In many cases, risk management strategies can be employed to mitigate these risks. Organizations often weigh the potential benefits against the risks involved and may choose to proceed if effective control measures can be implemented. For example, high-stakes activities in fields like medicine, aviation, or construction may involve risks but can be justified if there is a clear necessity and if precautions are in place to reduce the probability or impact of negative outcomes. Therefore, rather than a blanket prohibition, it is essential to assess the situation and implement adequate risk management practices.
Similar Questions
Risk assessment determines possible mishaps, their likelihood and consequences, and the tolerances for such events?TRUEFALSE
Answer True/False to the following question.A risk is a statement about a probability.
True or False: The more risk factors an individual has, their risk of falling increases.TrueFalse
People will not do the most routine tasks or take the least significant risks if they do not __________. Fill in the blank.
Only events that result in uncertain outcomes represent risks that should be managed. Select one: True False
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.