What is the measure of the team’s ability to complete work at a certain pace?
1 point
- Capacity and velocity
- Story and epic
- A product roadmap
- A release plan
Solution
The measure of a team's ability to complete work at a certain pace is referred to as "Capacity and Velocity".
Here's why:
-
Capacity refers to the total amount of work a team can handle during a specific time period. It is usually measured in hours or story points (a unit of measure for expressing the overall size of a user story, feature, or other piece of work).
-
Velocity, on the other hand, is a measure of the amount of work a team can tackle during a single sprint and is the key metric in Scrum. Velocity is calculated at the end of the Sprint by summing up the Points for all fully completed User Stories.
So, in the context of Agile project management and Scrum, Capacity and Velocity are used to measure a team's ability to complete work at a certain pace.
Similar Questions
What long-term objective for the Scrum Team is included in the Product Backlog? 1 pointProduct requirements documentProduct GoalProduct OwnerSprint Goal
Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask
What key component in the project management cycle is a meeting scheduled with staff to train on a new product?1 pointSuccess CriteriaDeliverableScopeResource
Which of the five elements of high-performance teams do you think would be most difficult for a leader to implement in a virtual team?
What key component in the project management cycle is a meeting scheduled with staff to train on a new product?1 pointSuccess CriteriaDeliverableResourceScope
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.