If it takes 18 days for 12 people to manufacture a machine, how many days will it take 9 people?

Question

If it takes 18 days for 12 people to manufacture a machine, how many days will it take 9 people?
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To solve this problem, we first need to find out how many man-days it takes to manufacture a machine.

Step 1: Calculate man-days Man-days is a measure of how much work is done by a certain number of people in a certain number of days. In this case, we multiply the number of people by the number of Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

If it takes 18 days for 12 people to manufacture a machine, how many days will it take 9 people?

9 persons can make 18 toys in 4 days working 8 hours a day. How many toys can 12 persons make in 6 days working 12 hours a day?

15 people can build 60 metres of track per day.Work out how many days it will take 45 people to build the whole track.

If 18 binders bind 900 books in 10 days, how many binders will be required to bind 660 books in 12 days?

A does a work in 12 days and B does the same work in 18 days.In how many days they together will do the same work?

1/3