6 persons working 5 hours a day can complete a work in 16 days .how many days will 4 persons wil take to complete the same work if each 6 hours a day​

Question

6 persons working 5 hours a day can complete a work in 16 days .how many days will 4 persons wil take to complete the same work if each 6 hours a day​
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

Sure, let's solve this step by step:

Step 1: First, let's find out the total hours required to complete the work by 6 persons working 5 hours a day for 16 days.

Total hours = Number of persons * hours per day * number of days Total hours = 6 persons * 5 hours/day * 16 days = 480 hours

Step 2: No Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

6 persons working 5 hours a day can complete a work in 16 days .how many days will 4 persons wil take to complete the same work if each 6 hours a day​

Sixteen men can complete a work in 22 days working 12 hours a day.  In how many days can 24 men complete the same work working 16 hours a day?

9 persons can make 18 toys in 4 days working 8 hours a day. How many toys can 12 persons make in 6 days working 12 hours a day?

45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day

f 6 men can complete a work in 15 hours. Then how many hours it will take if 10 men working at the same speed complete the work?

1/3