6 persons working 5 hours a day can complete a work in 16 days .how many days will 4 persons wil take to complete the same work if each 6 hours a day​

Question

How many days will 4 persons take to complete the same work if each works 6 hours a day?

6 persons working 5 hours a day can complete a work in 16 days.

🧐 Not the exact question you are looking for?Go ask a question

Solution

Sure, let's solve this step by step:

Step 1: First, let's find out the total hours required to complete the work by 6 persons working 5 hours a day for 16 days.

Total hours = Number of persons * hours per day * number of days Total hours = 6 persons * 5 hours/day * 16 days = 480 hours

Step 2: Now, let's find out how many days 4 persons working 6 hours a day will take to complete the same work.

Number of days = Total hours / (Number of persons * hours per day) Number of days = 480 hours / (4 persons * 6 hours/day) = 20 days

So, 4 persons working 6 hours a day will take 20 days to complete the same work.

This problem has been solved

Similar Questions

Sixteen men can complete a work in 22 days working 12 hours a day.  In how many days can 24 men complete the same work working 16 hours a day?

12 girls can do a a piece of work in 30 days, working 8 hours a day . In how many days 18 girls can do the same piece of work while working 4 hours a day?

9 persons can make 18 toys in 4 days working 8 hours a day. How many toys can 12 persons make in 6 days working 12 hours a day?

45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day

8) 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days . in how many days will 10 women complete it ?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.