A can do work in 20 days. Then, he is assisted by B to complete the remaining work in 12 days. In how much time can B alone do the work?

Question

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

Let's solve the problem step by step:

  1. Let's assume that the total work to be done is represented by the variable "W".

  2. We are given that A can complete the work in 20 days. Therefore, A's work rate can be calculated as 1/20 of the total work per day.

  3. A and B together complete the remainin Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.

Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  

This problem has been solved

Similar Questions

A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How manydays would B alone take to do the same work?

A can do a work in 15 days and B in 20 days. In how many days will they work together to finish the work

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

A and B can do a piece of work in 20 days, B and C can do it in 60 days. If B alone can do it in 90 days, in how many days will A and C do it together?

A, B and C can do a piece of work in 11, 20 and 55 days respectively. In how many days work will be finished if A is assisted by B and C on alternative day

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.