550 people can complete a work in 100 days. After 10 days, 50 more people joined. In how many more days the work will be completed?
Question
550 people can complete a work in 100 days. After 10 days, 50 more people joined. In how many more days the work will be completed?
Solution
To solve this problem, we can use the concept of man-days.
Given that 550 people can complete the work in 100 days, we can calculate the total man-days required to complete the work. This can be done by multiplying the number of people by the number of days: 550 * 100 = 55,000 man-days.
After 10 days, the work has already been in progress. So, we need to calculate the remaining man-days required to complete the work.
In the first 10 days, 550 people worked, which means they contributed 550 * 10 = 5,500 man-days.
Now, 50 more people joined, making the total number of people working on the project 550 + 50 = 600.
To find out how many more days it will take to complete the work, we need to calculate the remaining man-days and divide it by the number of people working.
The remaining man-days can be calculated by subtracting the man-days already contributed from the total man-days required: 55,000 - 5,500 = 49,500 man-days.
To find out how many more days it will take to complete the work, we divide the remaining man-days by the number of people working: 49,500 / 600 = 82.5 days.
Since we cannot have half a day, we round up to the nearest whole number. Therefore, it will take approximately 83 more days to complete the work with the additional 50 people.
So, in total, the work will be completed in 10 + 83 = 93 days.
Similar Questions
45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day
A, B and C can do a piece of work in 11, 20 and 55 days respectively. In how many days work will be finished if A is assisted by B and C on alternative day?
20 men can complete a task in 30 days. If one man leaves the site at the end of each day, then what fraction of work will be completed?
A and B can do a piece of work in 20 days, B and C can do it in 60 days. If B alone can do it in 90 days, in how many days will A and C do it together?
X can do a piece of work in 8 days, Y can do it in 10 days and Z can do it in 20 days. In how many days can X, Y and Z together complete the work?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.