During which stage of the project do these stakeholders have the maximum ability to influence a project?

Question

🧐 Not the exact question you are looking for?Go ask a question

Solution

The stakeholders have the maximum ability to influence a project during the initiation and planning stages.

Step 1: Initiation Stage This is the first stage of a project where the project's value and feasibility are measured. Stakeholders can influence the project at this stage by defining clear project goals, identifying potential risks, and developing a strong project concept.

Step 2: Planning Stage This is the stage where all the detailed planning happens. Stakeholders can influence the project at this stage by helping to develop a comprehensive project plan, which includes defining the project scope, developing a project schedule, and planning for resources and costs.

In these early stages, changes can be made more easily and with less impact on the project's overall timeline and budget, hence giving stakeholders the maximum ability to influence the project.