Which of the following is not a method of creating a project budget?
- Top-down budgeting
- Comparison budgeting
- Actual budgeting
- Roll-up budgeting
Solution
Identifying the Question
The question asks which of the listed options is not a recognized method of creating a project budget.
Analyzing the Options
- Top-down budgeting: This method involves senior management setting the budget based on overall strategic objectives.
- Comparison budgeting: This is not a standard budgeting method. It may refer to comparing budgets, but it is not a recognized technique for creating one.
- Actual budgeting: This usually refers to budgeting based on historical data and actual results from previous projects.
- Roll-up budgeting: This method involves aggregating budgets from different departments or project segments to form a comprehensive budget for the entire project.
Conclusion
Based on the analysis, Comparison budgeting is not a recognized method of creating a project budget.
Final Answer
Comparison budgeting is not a method of creating a project budget.
Similar Questions
Question 5What term refers to the budget, people, materials, and other items necessary to complete a project?
Which of the following should not be considered when setting a current budget?
The cost baseline is developed during which process?Develop scheduleDetermine budgetEstimate costsMonitor & control project work
The third major objective of budgets or budgeting.Select one:a.Allocation of Resourcesb.Planning Aheadc.Business Coordinationd.Performance Evaluation
A budget is an example of a:Question 4Select one:a.single-use plan.b.contingency plan.c.standing plan.d.strategic plan.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.