Knowee
Questions
Features
Study Tools

Which of the following is the formula for the management reserve index?Multiple choice question.EV/PVEV/ACAC/EACCV/MREV/BAC

Question

Which of the following is the formula for the management reserve index?

Multiple choice question.

  • EV/PV
  • EV/AC
  • AC/EAC
  • CV/MR
  • EV/BAC
🧐 Not the exact question you are looking for?Go ask a question

Solution

To find the correct formula for the management reserve index, let's analyze the options given.

  1. Break Down the Problem

    • We need to identify which formula accurately represents the management reserve index using the given choices.
  2. Relevant Concepts

    • The management reserve is typically calculated as a component of project management metrics, often involving Earned Value (EV), Planned Value (PV), Actual Cost (AC), Estimate at Completion (EAC), Cost Variance (CV), Management Reserve (MR), and Budget at Completion (BAC).
  3. Analysis and Detail

    • By analyzing the formulas provided:
      • EV/PV \text{EV/PV} : Represents the Cost Performance Index (CPI) or Schedule Performance Index (SPI), not the management reserve.
      • EV/AC \text{EV/AC} : Represents the Cost Performance Index (CPI), indicating efficiency of the project but not directly related to management reserves.
      • EAC/CV \text{EAC/CV} : Involves Estimate at Completion and Cost Variance but does not directly define direct indices.
      • MV/EV \text{MV/EV} : Represents a proportion of management value but is unclear as a standard formulation.
      • R/BAC \text{R/BAC} : This could relate to Reserves against the Budget at Completion.
  4. Verify and Summarize

    • None of the above options directly describe a well-established formula for the management reserve index.

Based on standard project management practices, the management reserve index is usually derived from the reserves compared to the overall project budget or some relevant performance metric.

Final Answer

The management reserve index is implicated with a ratio of reserves to overall project metrics, though not clearly represented by any option. Therefore, none of the provided options appear to accurately represent the management reserve index as commonly defined in project management. A more appropriate formula might be MR/BAC \text{MR/BAC} .

This problem has been solved

Similar Questions

Which of the following values is the "best" management reserve index from the project manager's perspective?Multiple choice question.0.100.501.001.502.00

Inspiratory reserve volume averages _________ mL.1000 -11001100 - 12002500 - 3000500

Which of the following is plural?*1 point(A) Index(B) Analysis(C) Crisis(D) Criteria

Which of the following is an asset utilization ratio?Multiple Choicereturn on assetsreceivables turnoverreturn on equitycurrent ratio

In the WACC formula, We stand for _____________.a.Cost of debtb.Weight of equity financingc.Weight of debt financingd.Cost of equity

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.