Ten men take 4 days to complete the task of tarring a road. How many days would8 men take?
Question
Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?
Solution
To solve this problem, we first need to understand the relationship between the number of workers and the time it takes to complete a task. In this case, the relationship is inversely proportional, meaning that as the number of workers increases, the time it takes to complete the task decreases.
Step 1: Find the total man-days it takes to complete the task.
We know that 10 men take 4 days to complete the task. So, the total man-days is 10 men * 4 days = 40 man-days.
Step 2: Find out how many days it would take 8 men to complete the task.
We know that the task takes 40 man-days to complete. So, if 8 men were to do the task, it would take 40 man-days / 8 men = 5 days.
So, 8 men would take 5 days to complete the task of tarring the road.
Similar Questions
If a wall is built in ten hours by 8 men how many hours will it take four men to build it?
A house takes eight hours to be built by four men. How much time would it take one man to build it?
8) 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days . in how many days will 10 women complete it ?
10 men could do a job in 8 hours. How long will it take them if 2 other men joined them?
f 6 men can complete a work in 15 hours. Then how many hours it will take if 10 men working at the same speed complete the work?