A team member can work on several projects is a disadvantage of functional project structure.Group of answer choicesTrueFalse

Question

A team member can work on several projects is a disadvantage of functional project structure.

Group of answer choices
True
False

🧐 Not the exact question you are looking for?Go ask a question

Solution

In a functional project structure, the organization is divided into departments categorized by specific functions, such as marketing, finance, and engineering. While this structure can operate efficiently within departments, a key disadvantage is that team members may be overextended due to their involvement in multiple projects.

This arrangement can lead to several issues:

  1. Divided Attention: Team members working on various projects may struggle to balance their responsibilities, leading to diminished focus and productivity on each individual project.

  2. Resource Conflicts: When multiple projects vie for the same resources, conflicts can arise, potentially delaying project timelines and increasing stress for team members.

  3. Lack of Ownership: Since team members may not be fully dedicated to a single project, they might feel less responsibility toward its success, which can impact overall project quality and results.

In conclusion, the statement that "a team member can work on several projects is a disadvantage of functional project structure" is True. This scenario often complicates project execution and can hamper team performance due to competing demands on resources and attention.

This problem has been solved

Similar Questions

Which of these is not one of the constraints of a project? Select one: a. Resources b. Budget c. Scope d. Team

Projects have characteristics that separate them from operations. From the list below, please select the characteristics of a project

ype of organizational structure most suitable for project-based organizations is Functional Matrix Network Team-based

Select the best answer.True or False? Every team member should take an active role in leveraging a project. True False

During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.