If 8 SSB or 12 CISF companies can patrol the Indo-Tibet border in 3 days, then how long will 6 SSB and 9 CISF companies take to do the same?

Question

If 8 SSB or 12 CISF companies can patrol the Indo-Tibet border in 3 days, then how long will 6 SSB and 9 CISF companies take to do the same?

🧐 Not the exact question you are looking for?Go ask a question

Solution

First, let's understand the rate at which the SSB and CISF companies can patrol the Indo-Tibet border.

According to the question, 8 SSB companies can patrol the border in 3 days. So, the rate at which SSB companies work is 8 companies/3 days = 2.67 companies/day.

Similarly, 12 CISF companies can patrol the border in 3 days. So, the rate at which CISF companies work is 12 companies/3 days = 4 companies/day.

Now, we need to find out how long 6 SSB and 9 CISF companies will take to patrol the border.

The combined rate of 6 SSB and 9 CISF companies is (6/2.67) + (9/4) = 2.25 + 2.25 = 4.5 days.

So, 6 SSB and 9 CISF companies will take 4.5 days to patrol the Indo-Tibet border.

This problem has been solved

Similar Questions

10 men could do a job in 8 hours. How long will it take them if 2 other men joined them?

Abhi and Bhanu can do a piece of work in 6 and 12 days, respectively. In how many days the work can be completed if Abhi and Bhanu work together?

If A can do a piece of work in 10 days and B can do the same work in 15 days, how long will they take to complete it together?

It takes six analysts forty-two days to write a report.If the report had to be ready in 7 days, how many analysts would be needed?

13 men can complete a work in 7 days. 1 man can complete it in:  Ops:   A. 35 days    B. 14 days    C. 65 days    D. 91 days