In which of the following project phases is the project schedule developed?a.Designb.Conceptualc.Implementationd.Planning
Question
In which of the following project phases is the project schedule developed?
- a. Design
- b. Conceptual
- c. Implementation
- d. Planning
Solution
The project schedule is developed during the Planning phase. So, the answer is d. Planning.
Here's a step-by-step breakdown of each phase:
a. Design: This is where the project's key features, requirements, and timeline are determined.
b. Conceptual: This phase involves brainstorming and exploring ideas for the project.
c. Implementation: This is where the actual work of the project begins based on the plan.
d. Planning: This is where the project schedule is developed, including defining tasks, resources, and timelines. This is the phase where project managers determine what work needs to be done, by whom, and by when.
Similar Questions
The project ______________ is the first stage of a project cycleQuestion 7Answera.Evaluation stageb.Idea stagec.Execution staged.Selection stage
Which of the following components of a project plan is completed first? Work breakdown structureRisk management planProject budgetProject schedule
The phase of the SDLC when the system is actually built or purchased is the ________________.a.designb.constructionc.implementationd.analysis
The project's goal or "need" is identified during______________ phase.InitiationPlanningClosureAll of the above
Which of the following are included in the project plan? Select all that apply.1 pointTasksRetrospectivesPeopleTime