In which of the following project phases is the project schedule developed?a.Designb.Conceptualc.Implementationd.Planning

Question

In which of the following project phases is the project schedule developed?

  • a. Design
  • b. Conceptual
  • c. Implementation
  • d. Planning
🧐 Not the exact question you are looking for?Go ask a question

Solution

The project schedule is developed during the Planning phase. So, the answer is d. Planning.

Here's a step-by-step breakdown of each phase:

a. Design: This is where the project's key features, requirements, and timeline are determined.

b. Conceptual: This phase involves brainstorming and exploring ideas for the project.

c. Implementation: This is where the actual work of the project begins based on the plan.

d. Planning: This is where the project schedule is developed, including defining tasks, resources, and timelines. This is the phase where project managers determine what work needs to be done, by whom, and by when.

This problem has been solved

Similar Questions

The project ______________ is the first stage of a project cycleQuestion 7Answera.Evaluation stageb.Idea stagec.Execution staged.Selection stage

Which of the following components of a project plan is completed first? Work breakdown structureRisk management planProject budgetProject schedule

The phase of the SDLC when the system is actually built or purchased is the ________________.a.designb.constructionc.implementationd.analysis

The project's goal or "need" is identified during______________ phase.InitiationPlanningClosureAll of the above

Which of the following are included in the project plan? Select all that apply.1 pointTasksRetrospectivesPeopleTime

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.