The project's goal or "need" is identified during______________ phase.InitiationPlanningClosureAll of the above

Question

The project's goal or "need" is identified during______________ phase.

  • Initiation
  • Planning
  • Closure
  • All of the above
🧐 Not the exact question you are looking for?Go ask a question

Solution

Break Down the Problem

  1. Identify what the question is asking: The question is about which phase of a project lifecycle identifies the project's goal or need.
  2. List the given options: Initiation, Planning, Closure, All of the above.

Relevant Concepts

  1. Understand the phases of project management:
    • Initiation: This phase involves defining the project at a broad level, including its goals and needs.
    • Planning: This phase involves outlining how to achieve the project's goals but does not typically identify the need itself.
    • Closure: This phase is about concluding the project, evaluating its success, and does not involve identifying needs.

Analysis and Detail

  1. Since the project goal or need is primarily identified during the Initiation phase, we can conclude that it is the key phase where the foundational purpose of the project is established.

Verify and Summarize

  1. Review the definitions of the project phases to confirm the understanding:
    • The Initiation phase identifies the project's need.
    • The Planning phase provides detailed planning on how to meet that need.
    • The Closure phase wraps up the project.

Final Answer

The project's goal or "need" is identified during the Initiation phase.

This problem has been solved

Similar Questions

The project's goal or "need" is identified during______________ phase.InitiationPlanningClosureAll of the above

Which of the following are key components of project initiation? Select all that apply. 1 pointScopeGoalsSuccess criteriaProject charter

Requirement gathering is an important phase. Explain the requirement gathering technique.[It's a short question]

Fill in the missing word: After a feasibility study, a project is formalised by means of a …a.programmeb.letterc.project charterd.meeting

Which of the following describes the primary goal of a firm? A. tactical plan B. mission statement C. operating plan D. bottom-up plan E. contingency plan

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.