Which of these methods uses the 3-time estimate?a.CPMb.PERTc.Forward pass methodd.Backward pass method

Question

Which of these methods uses the 3-time estimate?a.CPMb.PERTc.Forward pass methodd.Backward pass method
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To determine which method uses the 3-time estimate, let's analyze each option:

a. CPM (Critical Path Method): The CPM method does not use the 3-time estimate. It focuses on determining the critical path and calculating the project duration based on the estimated time for each activity.

b. PERT (Pr Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.

Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  

This problem has been solved

Similar Questions

Which of these methods uses the 3-time estimate?a.CPMb.PERTc.Forward pass methodd.Backward pass method

Which of the following is the BEST method to estimate a 1-oz. serving size of nuts?

The determinates of the estimating method used are information available, estimator workload, time available and purpose for the estimate True False

Which of these method of Object class is used to obtain class of an object at run time?

Which of these methods of Thread class is used to Suspend a thread for a period of time?Select one:a. suspend()b. terminate()c. sleep()d. stop()

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.