Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates

Question

Multiple Choice Question

PERT uses ____ for each activity.

  • three time estimates
  • four time estimates
  • one time estimate
  • two time estimates
🧐 Not the exact question you are looking for?Go ask a question

Solution

Break Down the Problem

  1. Identify the purpose of PERT (Program Evaluation and Review Technique).
  2. Understand the number of time estimates used in PERT calculations.

Relevant Concepts

  1. PERT is a project management tool that emphasizes time management.
  2. It typically involves three time estimates: optimistic, pessimistic, and most likely.

Analysis and Detail

  1. The three time estimates are defined as follows:
    • Optimistic Time (O): The minimum possible time required to complete the activity, assuming everything proceeds better than expected.
    • Pessimistic Time (P): The maximum possible time needed, assuming everything goes wrong.
    • Most Likely Time (M): The best estimate of the time required, assuming normal problems and opportunities.

Verify and Summarize

The correct option, given the purpose of PERT, is that it uses three time estimates.

Final Answer

The correct choice is: three time estimates.

This problem has been solved

Similar Questions

Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates

Multiple Choice QuestionManagement uses a(n) ______ budget to establish the standard overhead rate.Multiple choice question.fixedflexiblemaster

ultiple Choice QuestionProject progress reports are designed and communicated in:Multiple choice question.written form only.written or oral form.person.

_____ are collected from several entities at the same point in timeGroup of answer choicesCategorical DataRandom DataCross-sectionalTime Series Data

Which of the following are included in the project plan? Select all that apply.1 pointTasksRetrospectivesPeopleTime

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.