Which of the following is a key deliverable of Sprint Planning?1 pointA burndown chartThe Sprint BacklogThe project charterRetrospective notes

Question

Which of the following is a key deliverable of Sprint Planning?

1 point

  • A burndown chart
  • The Sprint Backlog
  • The project charter
  • Retrospective notes
🧐 Not the exact question you are looking for?Go ask a question

Solution

The key deliverable of Sprint Planning is "The Sprint Backlog".

Here's a step-by-step explanation:

  1. Sprint Planning is a meeting in Scrum, a framework for Agile project management. During this meeting, the team decides what they will work on during the upcoming sprint (a set period of time, usually 2-4 weeks).

  2. The output of this meeting is the Sprint Backlog, which is a list of tasks and goals the team commits to achieve by the end of the sprint.

  3. A burndown chart, on the other hand, is a graphical representation of work left to do versus time. It is usually updated as the sprint progresses, not during the planning.

  4. The project charter is a document that formally authorizes a project, providing a high-level overview. It's not specific to Scrum or sprint planning.

  5. Retrospective notes are taken during the Sprint Retrospective, a meeting held at the end of the sprint to discuss what went well, what didn't, and how the team can improve in the next sprint.

So, out of the options provided, the Sprint Backlog is the key deliverable of Sprint Planning.

This problem has been solved

Similar Questions

What is one step in a design sprint planning process?1 pointCall in the expertsBuild the final productReview previous sprintsReview new technologies

In a sprint brief, what section includes what the team wants to create by the end of the sprint?1 pointProductsOutputsKey deliverablesKey creations

Question 6An entry-level UX designer’s role in design sprint planning is to set the goals.1 pointTrueFalse

Question 3A design sprint brief should include the current state of the project and an estimated launch plan.1 pointTrueFalse

Which of the following Scrum artifacts is a central list of work that needs to be done?answerProduct backlogSprint backlogProject evaluationSprint goal

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.