Question
The costs incurred prior to the split-off point are referred to as
*1 point
- Joint Product Cost
- None of the above
- Separable Cost
- Split-Off Cost
- Joint Cost
Solution
The correct answer to the question is Joint Cost.
Explanation:
-
Joint Costs are the costs incurred before the split-off point in a manufacturing process where multiple products are produced from a single raw material. This is a relevant concept in cost accounting and helps in understanding how costs should be allocated to different products that are produced simultaneously.
-
Split-Off Point is the point in the manufacturing process where the joint products become distinct products.
-
Separable Costs are costs that can be directly attributed to individual products after the split-off point.
Thus, the expenses incurred before the products become distinct are collectively known as joint costs.
Similar Questions
The costs incurred prior to the split-off point are referred to as *1 pointJoint Product CostNone of the aboveSeparable CostSplit-Off CostJoint Cost
The point at which individual products are first identifiable in a joint process is referred to as the split-off point.Group of answer choicesTrueFalse
Fill in the Blank QuestionFill in the blank question.Costs incurred to produce or purchase two or more products at the same time are called costs.
Product Costs set a(n) ___________ to a product’s price.a.demand curveb.floorc.ceilingd.experience curvee.break-even cost
Fill in the Blank QuestionFill in the blank question.The costs which are eliminated if a segment is eliminated are called costs.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.