Which is the name of the Task which comes before the current task?Question 8Select one:a.Successorb.Critical Pathc.Predecessord.Milestone
Question
Which is the name of the Task which comes before the current task?
Question 8
Select one:
a. Successor
b. Critical Path
c. Predecessor
d. Milestone
Solution
Analyzing the Question
To identify the term that describes a task preceding another in project management, we examine the provided options.
- Successor - This is a task that follows another task.
- Critical Path - This is the sequence of stages determining the minimum time needed for an operation.
- Predecessor - This refers to a task that occurs before a particular task in a project.
- Milestone - This represents a significant point or event in a project timeline, but does not specifically refer to a preceding task.
Conclusion
The correct choice is c. Predecessor, as it accurately describes a task that occurs before another task in the scheduling of project activities.
Similar Questions
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse
What is another term for Process Goals?Question 9Answera.Mini Objectivesb.Micro Objectivesc.Milestonesd.Mid term goals
The project ______________ is the first stage of a project cycleQuestion 7Answera.Evaluation stageb.Idea stagec.Execution staged.Selection stage
A(n) _____ determines the early start and early finish dates for each activity in a project.
Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.