Knowee
Questions
Features
Study Tools

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse

Question

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.

Group of answer choices

  • True
  • False
🧐 Not the exact question you are looking for?Go ask a question

Solution

Answer

The statement is True.

Explanation

In project management and scheduling, when an activity has only one predecessor, the early start of that activity is determined by the early finish of its predecessor. The early finish of the predecessor activity represents the latest time by which the predecessor must be completed in order for the dependent activity to begin as soon as possible. Therefore, the timing directly links:

  • Early Start of the dependent activity = Early Finish of the predecessor activity

This concept is fundamental in techniques like the Critical Path Method (CPM) and helps in effectively scheduling tasks by ensuring there are no delays caused by the predecessor activities.

This problem has been solved

Similar Questions

A(n) _____ determines the early start and early finish dates for each activity in a project.

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False

Which is the name of the Task which comes before the current task?Question 8Select one:a.Successorb.Critical Pathc.Predecessord.Milestone

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

Which past tense form expresses the beginning or end of a past action?Question 7Select one:a.imperfectb.preterite

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.