Resource levelling has the potential of turning non-critical activities into critical activities. Group of answer choicesTrueFalse
Question
Resource levelling has the potential of turning non-critical activities into critical activities.
Group of answer choices
- True
- False
Solution
Understanding Resource Levelling
Resource levelling is a project management technique used to address conflicts in resource allocation. This technique aims to ensure that resources are used efficiently, smoothing out resource usage to prevent over-allocation or under-allocation.
Impact on Critical Activities
-
Definition of Critical Activities: Critical activities are those that directly impact the project completion time. Any delay in critical activities will result in a delay in the entire project.
-
Non-Critical Activities: These are activities that do not impact the project's overall timeline directly and have some amount of flexibility in their scheduling.
Analysis of the Statement
Resource levelling can indeed affect the scheduling of both critical and non-critical activities. By reallocating resources to non-critical tasks or delaying non-critical activities, it can inadvertently make them critical.
Conclusion
Given the above analysis, the statement that "Resource levelling has the potential of turning non-critical activities into critical activities" is True.
Final Answer
True.
Similar Questions
Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse
During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse
New critical path/paths might arise due to resource levelling .Group of answer choicesTrueFalse
Activities on the critical path are the most important activities in a project. (True/False)
Fill in the Blank QuestionFill in the blank question.Recall that advances increase the quality of other resources.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.