Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse
Question
Solution 1
True. Resource leveling is a technique in project management that is used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts. When resource leveling is applied to a project, it can often cause the slack or float time of non Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv
Similar Questions
Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse
Resource levelling has the potential of turning non-critical activities into critical activities. Group of answer choicesTrueFalse
New critical path/paths might arise due to resource levelling .Group of answer choicesTrueFalse
During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse
Crashing of project activities will not change the critical path in the project network.Group of answer choicesTrueFalse