It takes some bricklayers 28 hours to build a 168 m wall.How long will it take them to build a 42 m wall?
Question
It takes some bricklayers 28 hours to build a 168 m wall.
How long will it take them to build a 42 m wall?
Solution
1. Break Down the Problem
To find out how long it will take to build a 42 m wall, we first need to determine the rate at which the bricklayers are working. Then we can use that rate to find the time required for the smaller wall.
2. Relevant Concepts
We will use the concept of work rate, where the rate can be calculated as:
Here, the "Total Work Done" is the length of the wall built.
3. Analysis and Detail
-
Calculate the rate of work using the given information:
-
Now, we'll use this rate to determine how long it will take to build a 42 m wall:
4. Verify and Summarize
The calculated rate was consistent with the work done in the initial scenario (168 m in 28 hours). Therefore, the calculations appear to be accurate.
Final Answer
It will take them 7 hours to build a 42 m wall.
Similar Questions
If a wall is built in ten hours by 8 men how many hours will it take four men to build it?
A house takes eight hours to be built by four men. How much time would it take one man to build it?
If 72 men can build a wall of 280 m in length in 21 days, how many men could take 18 days to build a similar type of wall of the length of 100 m?
A and B can build a certain wall in 20 days and 30 days respectively. In how many days can they together build two such walls?
You take 4 hours to put together 32 units. How many hours would it take you to put together 56 units?7 hours8 hours14 hours24 hours
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.