If 72 men can build a wall of 280 m in length in 21 days, how many men could take 18 days to build a similar type of wall of the length of 100 m?
Question
If 72 men can build a wall of 280 m in length in 21 days, how many men could take 18 days to build a similar type of wall of the length of 100 m?
Solution
First, let's find out how many man-days it takes to build a 1 meter length of the wall.
72 men can build 280 m in 21 days, so the total man-days is 72 men * 21 days = 1512 man-days.
Therefore, it takes 1512 man-days to build 280 m, so to build 1 m, it would take 1512 man-days / 280 m = 5.4 man-days.
Now, we want to find out how many men it would take to build a 100 m wall in 18 days.
First, let's find out how many man-days it would take to build a 100 m wall. We know that 1 m takes 5.4 man-days, so 100 m would take 5.4 man-days/m * 100 m = 540 man-days.
If we have 18 days to build the wall, then the number of men required would be 540 man-days / 18 days = 30 men.
So, it would take 30 men 18 days to build a similar type of wall of the length of 100 m.
Similar Questions
If a wall is built in ten hours by 8 men how many hours will it take four men to build it?
A house takes eight hours to be built by four men. How much time would it take one man to build it?
It takes some bricklayers 28 hours to build a 168 m wall.How long will it take them to build a 42 m wall?
A certain task can be completed in 60 mandays. How many men are required to complete 23 of thistask within 5 days?
If 24 workers can build a house in 40 days, how many workers will be required to build the same house in 20 days?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.