Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
Question
Solution 1
False.
Explanation:
Crashing in the time-cost CPM (Critical Path Method) model is a technique used to shorten the schedule duration for the least incremental cost by adding resources. It does not directly aim to improve the project quality.
Crashing is typically used when a project is behind sch Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI
Similar Questions
Crashing of project activities will not change the critical path in the project network.Group of answer choicesTrueFalse
CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
Masterformat is used in the construction document phase to organize project specifications.Group of answer choicesTrueFalse
Uniformat is used in the construction document phase to organize project specifications.Group of answer choicesTrueFalse
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.