Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
Question
Using the time-cost CPM model, crashing is used to improve the project quality.
Group of answer choices
- True
- False
Solution
False.
Explanation:
Crashing in the time-cost CPM (Critical Path Method) model is a technique used to shorten the schedule duration for the least incremental cost by adding resources. It does not directly aim to improve the project quality.
Crashing is typically used when a project is behind schedule or when there is a need to complete the project earlier than originally planned. While crashing can help to ensure that a project is completed on time, it does not necessarily improve the quality of the project. Therefore, the statement "Using the time-cost CPM model, crashing is used to improve the project quality" is false.
Similar Questions
CPM is suitable for which kind of projects?a.Micro projectsb.Large projectsc.Mini projectsd.Micro and Mini projects
Crashing of project activities will not change the critical path in the project network.Group of answer choicesTrueFalse
One method in selecting a project option is to use a numerical model. Briefly explain and Payback method noting the advantages and disadvantages.
Project Management Triangle consist ofa.Time, money, qualityb.Quality, Cost, Deliveryc.Scope, Time, Qualityd.Cost, Scope, Time
__________ is a project management method that relies on gathering fast feedback.AAmileBSubsistent
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.