Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse

Question

Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

False.

Explanation:

Crashing in the time-cost CPM (Critical Path Method) model is a technique used to shorten the schedule duration for the least incremental cost by adding resources. It does not directly aim to improve the project quality.

Crashing is typically used when a project is behind sch Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.

Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  

This problem has been solved

Similar Questions

Crashing of project activities will not change the critical path in the project network.Group of answer choicesTrueFalse

CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

Masterformat is used in the construction document phase to organize project specifications.Group of answer choicesTrueFalse

Uniformat is used in the construction document phase to organize project specifications.Group of answer choicesTrueFalse

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.