Select the best answer.Which of the following is often used to measure the impact of a process improvement project on business results? DOE CTQ ROI FMEA
Question
Select the best answer.
Which of the following is often used to measure the impact of a process improvement project on business results?
- DOE
- CTQ
- ROI
- FMEA
Solution
To determine which option is best suited for measuring the impact of a process improvement project on business results, let's analyze each option:
-
DOE (Design of Experiments): This is a statistical method used to plan experiments and analyze the effects of various factors on a process. While it helps in understanding variations and optimizing processes, it is not directly used to measure business results.
-
CTQ (Critical to Quality): These are the key measurable characteristics of a product or service that are essential for customer satisfaction. While CTQs are important in defining quality metrics, they don't necessarily quantify the impact on business results.
-
ROI (Return on Investment): This is a financial metric used to evaluate the profitability of an investment relative to its costs. ROI is often used in business to measure the financial return of a process improvement project by comparing the benefits gained to the costs incurred.
-
FMEA (Failure Mode and Effects Analysis): This is a systematic method for evaluating processes to identify where and how they might fail and assessing the relative impact of different failures. While useful for risk management, it does not directly measure business results.
Conclusion
The best answer is ROI. It directly measures the financial impact of process improvements on business results, making it the most relevant option among the choices provided.
Similar Questions
Select the best answer.Which of the following is often used to measure the impact of a process improvement project on business results? DOE CTQ ROI FMEA
In project quality management, _____ involves monitoring specific project results to ensure that they are complete, correct, and meet customer expectations.
During which phase of process improvement are bottlenecks and weaknesses identified?Process measurementProcess analysisProcess changeNone of the above
Which of the following choices best represents how work performance was improved?
Which of the following best describes the importance of assessing waste in a construction project?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.