Knowee
Questions
Features
Study Tools

In your completed RACI chart, how many stakeholders are accountable for the “code the landing page” task?1 point012 or more

Question

In your completed RACI chart, how many stakeholders are accountable for the “code the landing page” task?

1 point

  • 0
  • 1
  • 2 or more
🧐 Not the exact question you are looking for?Go ask a question

Solution

To determine how many stakeholders are accountable for the "code the landing page" task in a RACI chart, follow these steps:

  1. Understand the RACI Chart: A RACI chart is a matrix used to assign roles and responsibilities for tasks in a project. RACI stands for:

    • Responsible: The person(s) who do the work to complete the task.
    • Accountable: The person who is ultimately answerable for the correct and thorough completion of the task.
    • Consulted: The person(s) who provide information and expertise necessary to complete the task.
    • Informed: The person(s) who need to be kept up-to-date on the progress of the task.
  2. Identify the Task: Focus on the specific task "code the landing page."

  3. Locate the Task in the RACI Chart: Find the row or section in the RACI chart that corresponds to "code the landing page."

  4. Identify the Accountable Stakeholder(s): Look for the column(s) where the "A" (Accountable) designation is marked for the "code the landing page" task.

  5. Count the Accountable Stakeholder(s): Count how many stakeholders have been marked as "A" for this task.

In a well-structured RACI chart, typically only one stakeholder is marked as accountable for each task to ensure clear responsibility. Therefore, the answer is:

1

So, in your completed RACI chart, there should be 1 stakeholder accountable for the "code the landing page" task.

This problem has been solved

Similar Questions

In the RACI model, which role reviews the work to confirm it is complete?1 pointResponsibleAccountableConsultedInformed

It is advisable to always involve as many key stakeholders as possible in the development of vision and mission statements.Question 11Answera.Trueb.False

How many subjects' scores are the users prompted to enter in the program?  (Refer to Code 1)Group of answer choices4321

What is the final outcome of the requirements analysis and specification phase?Drawing the data flow diagramThe SRS DocumentCoding the projectThe User Manual

Question: Which type of stakeholders perform the project work?Instruction: Choose the option that best answers the question. UpwardSidewaysDownwardOutward

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.