10 boys can do a work in 9 days. How many boys are required to finish the same work in 6 days? Ops: A. 18 boys B. 16 boys C. 15 boys D. 12 boys
Question
Solution 1
This problem can be solved using the concept of man-days which is a unit of work done by one person in one day.
Step 1: Calculate the total man-days required to finish the work. If 10 boys can finish the work in 9 days, then the total man-days required is 10 boys * 9 days = 90 man-days.
Step 2: Ca Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI
Similar Questions
10 boys can do a work in 9 days. How many boys are required to finish the same work in 6 days? Ops: A. 18 boys B. 16 boys C. 15 boys D. 12 boys
12 men or 18 women can do a job in 14 days. In how many days work will be finished by 8 men and 16 women
A can finish a work in 24 days, B in 9 days and C in 12 days. B & C start the work but are forced to leave after 3 days. The remaining work done by A in:
Select the correct answerFind median and mode of the messages received on 9 consecutive days 15, 11, 9, 5, 18, 4, 15, 13, 17.Options18, 1513, 1813, 615, 16
A is twice as good as B and together they can finish the work in 18 days. In how many days A will finish the same work?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.