What is a particular task/exercise in a project known as CPM?a.Activityb.Eventc.Taild.Head
Question
What is a particular task/exercise in a project known as CPM?
- a. Activity
- b. Event
- c. Tail
- d. Head
Solution
The correct answer is a. Activity.
Explanation:
-
Understanding CPM: CPM stands for Critical Path Method, which is a project management technique used to determine the longest stretch of dependent activities and measure the time required to complete them from start to finish.
-
Defining Terms:
- Activity: This refers to a specific task or exercise in a project that requires time and resources to complete.
- Event: This term denotes a significant point in time within the project where certain milestones are achieved.
- Tail: Generally, this term does not apply to CPM in a direct sense.
- Head: Similar to tail, this is often not directly related to CPM terminology.
Conclusion:
In CPM, activities are the core components that drive the project forward, making option a. Activity the correct choice.
Similar Questions
A sequence of complex, connected activities that have a common goal or purposes is known as a ___________?
Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
Activities on the critical path are the most important activities in a project. (True/False)
is the method where a project manager reviews all individual tasks and rolls the tasks into manageable chunks that lead to a milestone.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.