In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

Question

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

False

In a Critical Path Method (CPM) analysis, the activity's slack time is not determined by subtracting the early start from the early finish. Instead, slack time is calculated by subtracting the early start of the activity from its late start, or the early finish from its late finish. Slack tim Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse

In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse

Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse

1/3