In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
Question
Solution 1
False
In a Critical Path Method (CPM) analysis, the activity's slack time is not determined by subtracting the early start from the early finish. Instead, slack time is calculated by subtracting the early start of the activity from its late start, or the early finish from its late finish. Slack tim Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv
Similar Questions
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse
Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse