The required rate of return from a project is 10% and the internal rate of return of the project is 12%, hence the project should be
Question
The required rate of return from a project is 10% and the internal rate of return of the project is 12%, hence the project should be
Solution
1. Break Down the Problem
The question requires us to evaluate whether the project is acceptable based on its required rate of return (RRR) and internal rate of return (IRR).
2. Relevant Concepts
- Required Rate of Return (RRR): The minimum return an investor expects to achieve for the level of risk associated with the investment.
- Internal Rate of Return (IRR): The discount rate at which the net present value (NPV) of all cash flows (both positive and negative) from a project equals zero.
3. Analysis and Detail
Given:
- Required Rate of Return (RRR) = 10%
- Internal Rate of Return (IRR) = 12%
To determine the project's viability:
- Since the IRR (12%) is greater than the RRR (10%), the project is expected to generate a return higher than the investor's required rate. This indicates that the project is likely to add value and is a viable investment option.
4. Verify and Summarize
The IRR exceeding the RRR indicates that the project meets the financial benchmarks required for profitability. Therefore, it should be accepted as it suggests profitable returns.
Final Answer
The project should be accepted since the IRR (12%) is greater than the RRR (10%).
Similar Questions
What is the NPV of a project that costs $100,000 and returns $50,000 annually for 3 years if the opportunity cost of capital is 14%?
If you do not know the discount rate for a project, the right investment criterion to be used will be(1 Point)MIRRBCRIRRNPV
Calculate the Rate of Return on an initial investment of $6,000 valued at $6,500. Responses8.3%8.3%6.5%6.5%4.3%4.3%9.5%
Fill in the Blank QuestionFill in the blank question.The rate of return may be expressed as a negative number if the investment in value.
projectA initial cost 12000, scape value is 10% of initial cost, what is the projectA annual depreciation
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.