Question

How many phases are there in Scrum?

Options

  • Two
  • Four
  • Scrum is an agile method which means it does not have phases
  • Three
🧐 Not the exact question you are looking for?Go ask a question

Solution

Break Down the Problem

  1. Identify the options provided for the number of phases in Scrum.
  2. Determine the correct number of phases that Scrum includes based on its framework.

Relevant Concepts

Scrum is an Agile framework used primarily for managing software development projects. It is known for its iterative and incremental approach. The Scrum process itself consists of specific components, which include roles, events, and artifacts.

Analysis and Detail

Scrum is structured around several key events, providing a cycle of continuous improvement. The main components include:

  • Sprints: Time-boxed iterations.
  • Sprint Planning: Setting objectives for each sprint.
  • Daily Scrum: Regular team check-ins.
  • Sprint Review: Assessment of outcomes.
  • Sprint Retrospective: Reflection on the process.

While Scrum is organized around these core elements, it does not strictly adhere to a traditional phase-driven approach like Waterfall methodologies, which often have distinct phases.

Verify and Summarize

Scrum consists of a repeating cycle (the Sprint) and various ceremonies and artifacts associated with this cycle rather than clear-cut phases. Thus, the answer is not about the number of "phases" but rather the events and roles that make it effective.

Final Answer

Scrum does not fit the typical notion of phases in project management; instead, it operates in a cyclic manner. The correct answer is that Scrum does not have phases in the traditional sense, hence the answer would be "Scrum is an agile method which means it does not have phases."

This problem has been solved

Similar Questions

How many phases are there in Scrum?OptionsTwoFourScrum is an agile method which means it does not have phasesThree

Agile Software Development is based onOptionsIncremental DevelopmentLinear DevelopmentBoth Incremental and Iterative DevelopmentIterative Development

Agile Software Development is based onOptionsBoth Incremental and Iterative DevelopmentIterative DevelopmentIncremental DevelopmentLinear Development

In the Waterfall model, which phase comes immediately after the Design phase?Question 3Select one:a.Implementationb.Testingc.Maintenanced.Planning

Which are not the part of Scrum sprint cycle?Group of answer choicesG2M strategySprint RetroSprint PlanningSprint ReviewDaily Scrum

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.