The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
Question
Solution 1
The latest possible time an activity can start without delaying the project is known as the Latest Start Time.
Here's a step-by-step explanation:
-
In project management, every activity or task has a start time and a finish time.
-
The Latest Start Time (LST) is the latest time that you can st Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI
Similar Questions
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752
Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration