The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
Question
The latest possible time an activity can start without delaying the project
- a. Latest start time
- b. Latest finish time
- c. Project Cost
- d. Duration
Solution
The latest possible time an activity can start without delaying the project is known as the Latest Start Time.
Here's a step-by-step explanation:
-
In project management, every activity or task has a start time and a finish time.
-
The Latest Start Time (LST) is the latest time that you can start a particular activity without delaying the project.
-
To calculate the LST, you subtract the duration of the task from the Latest Finish Time (LFT). The formula is: LST = LFT - task duration.
-
The LFT is the latest time that an activity can finish without delaying subsequent activities or the entire project.
-
The LST is crucial in project scheduling and helps in identifying the slack time for activities. Slack time
Similar Questions
Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is
Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False
A(n) _____ determines the early start and early finish dates for each activity in a project.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.