The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration

Question

The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

The latest possible time an activity can start without delaying the project is known as the Latest Start Time.

Here's a step-by-step explanation:

  1. In project management, every activity or task has a start time and a finish time.

  2. The Latest Start Time (LST) is the latest time that you can st Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.

Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI  

This problem has been solved

Similar Questions

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752

Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.