The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False
Question
Solution 1
False. The earliest finish time for an activity is calculated by adding the activity's duration to its earliest start time. The activity slack, or float, is the amount of time that you can delay a task without delaying the project. More slack time means that project scheduling is more flexible. Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem. Know
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI is a
Similar Questions
The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is
Other things being equal, the higher the debt to equity ratio, the higher the risk of bankruptcy.Group startsTrue or False
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752