Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options

Question

Which path duration is considered as the project completion time?

  • a. Shortest path
  • b. Longest Path
  • c. Most likely path
  • d. None of the given options
🧐 Not the exact question you are looking for?Go ask a question

Solution

Break Down the Problem

  1. We need to determine which type of path duration signifies the completion of a project.
  2. Investigate the definitions of the various paths mentioned in the options.

Relevant Concepts

  1. Shortest Path: The path with the least total duration. It is not used to determine project completion.
  2. Longest Path: Also known as the critical path, this is the longest duration path through a project. It defines the minimum time required for the project to be completed.
  3. Most Likely Path: This term typically refers to an estimation in project management used in PERT (Program Evaluation Review Technique) but does not indicate completion.
  4. None of the Given Options: Needs to be evaluated based on the provided definitions.

Analysis and Detail

  1. The critical path method (CPM) is used to identify the longest path of dependent tasks and represents the shortest possible project duration.
  2. Therefore, the longest path in project management is directly related to project completion time.

Verify and Summarize

  • Given that the longest path represents the maximum time that must be spent on the project to ensure completion, the answer must be aligned with this principle.

Final Answer

b. Longest Path

This problem has been solved

Similar Questions

Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask

The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration

Critical path method is suitable for _____________ project schedulesa.Optimizingb.Minimisingc.Maximizationd.None of the given options

Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration

Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.