Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration
Question
Represents the amount of time an activity can be delayed without impacting the critical path or project completion.
- a. Slack
- b. Nodes
- c. Activities
- d. Duration
Solution
Break Down the Problem
- The question is focused on project management terminology.
- We need to identify which term among the options relates to the concept of time that can be delayed without affecting overall project timelines.
Relevant Concepts
- The critical path is the longest sequence of activities in a project that must be completed on time for the entire project to be completed on due date.
- In project management, "slack" refers to the amount of time that you can delay a task without delaying the project.
Analysis and Detail
- Option a: Slack - This term specifically refers to the amount of time that a task can be delayed without affecting the overall project completion date. It indicates flexibility in scheduling.
- Option b: Nodes - This is a graphical representation of a project, but it does not define time flexibility.
- Option c: Activities - These are tasks that must be completed, but it does not measure delay impact.
- Option d: Duration - This refers to the total time taken to complete an activity, not the flexibility of its delay.
Verify and Summarize
Based on the definitions and comparison of each option, the term that correctly represents the concept of time that can be delayed without impacting the critical path or project completion is "slack".
Final Answer
a. Slack
Similar Questions
Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration
Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.