What are the main statuses used on a Kanban board? Select all that apply. 1 pointTo doDoneIn progressPlanning
Question
Solution 1
The main statuses used on a Kanban board are:
- To do
- In progress
- Done
While "Planning" could be a part of the process in some teams, it is not traditionally a main status used on a Kanban board. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve st
problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you
Similar Questions
What are the main statuses used on a Kanban board? Select all that apply. 1 pointTo doDoneIn progressPlanning
What are the main statuses used on a Kanban board? Select all that apply. 1 pointPlanningIn progressDoneTo do
Which software programs can you use to create a Kanban board? Select all that apply. 1 pointKeynoteGoogle CalendarAsana Trello
Which elements are commonly used when scaling down digital real estate to smaller screens? Select all that apply.1 pointListsCarousels Hamburger menusCards
A query is used to _____ information from a database. Select all that apply.1 pointrequest retrievevisualizeupdate