Which of the following is NOT an element of a Kanban board?commitment pointsprint backlogcardswork in progress limitdelivery pointcolumns
Question
Which of the following is NOT an element of a Kanban board?
- commitment point
- sprint backlog
- cards
- work in progress limit
- delivery point
- columns
Solution
To determine which option is NOT an element of a Kanban board, let's analyze each option in relation to the key components of a Kanban system.
-
Commitment Point: This is usually not a term commonly associated with Kanban boards specifically. It indicates decision-making in the project management context but does not belong to the fundamental structure of a typical Kanban board.
-
Sprint Backlog: This term is specific to Scrum, another agile framework, and is not a part of the Kanban methodology. Kanban does not use the concept of sprints, as it focuses on continuous flow.
-
Cards: These represent work items on the Kanban board. Each card shows the progress of tasks and is a fundamental element of the board.
-
Work in Progress Limit (WIP Limit): This is a core principle of Kanban, which helps manage the amount of work in progress to improve efficiency.
-
Delivery Point: In a Kanban context, this would refer to the point at which work items are considered done, which is an aspect of managing the flow.
-
Columns: These represent different stages of workflow in a Kanban board and are essential for visualizing progress.
Based on this breakdown, the elements NOT found in a Kanban board are the Sprint Backlog and Commitment Point. However, since the primary focus seems to be on the Kanban board itself, the most direct answer would be:
Final Answer
Sprint Backlog is NOT an element of a Kanban board.
Similar Questions
What are the main statuses used on a Kanban board? Select all that apply. 1 pointTo doDoneIn progressPlanning
Which factor determines when work is pulled into the Kanban board?team capacitywork due datescompany objectivesstakeholder requirements
What do both scrum and kanban have in common?artifactsroleseventsworkflowsThis item can be moved. Use the space bar to grab it.Next
Identify two types of boards you can create within Jira. (Choose two.)Select 2 Correct ResponsesKanbanCompany-managedRoadmapScrumSprint
The first core practice of the Kanban Method is to ________ the flow of work.Question 6Answera.Visualizeb.Restrictc.Accelerated.Automate
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.