Which value for TCPI indicates the project is under budget?Multiple choice question.0.781.001.78
Question
Which value for TCPI indicates the project is under budget?
Multiple choice question.
- 0.78
- 1.00
- 1.78
Solution
Break Down the Problem
- Identify the concept of TCPI (To Complete Performance Index) and its implications for project management.
- Examine the provided options to determine which indicates that the project is under budget.
Relevant Concepts
TCPI is calculated using the formula:
Where:
- = Budget at Completion
- = Earned Value
- = Actual Cost
A TCPI value less than 1 indicates that the project is under budget, meaning the remaining work can be completed within the budget.
Analysis and Detail
-
Values:
- means the project is under budget.
- indicates the project is on budget.
- suggests the project is over budget.
-
Evaluating the options:
- 0.78 (Under budget)
- 1.00 (On budget)
- 1.78 (Over budget)
Verify and Summarize
Since a TCPI value less than 1 means that the project is under budget, we can conclude that the best choice is:
Final Answer
0.78 indicates the project is under budget.
Similar Questions
Which of the following should not be considered when setting a current budget?
Which of the following is not a method of creating a project budget?Top-down budgetingComparison budgetingActual budgetingRoll-up budgeting
Which of these is not one of the constraints of a project? Select one: a. Resources b. Budget c. Scope d. Team
Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive
The equation for developing a production budget is select an option plus select an option minus select an option.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.