Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive

Question

Which type of project cost estimate is the most accurate?

  1. Order of magnitude
  2. Preliminary
  3. Conceptual
  4. Definitive
🧐 Not the exact question you are looking for?Go ask a question

Solution

Break Down the Problem

  1. Identify the types of project cost estimates.
  2. Determine the accuracy of each type.

Relevant Concepts

  • Order of Magnitude Estimate: Typically used in the early stages of a project, these estimates can vary greatly, usually within a range of -25% to +75%.
  • Preliminary Estimate: More refined than the order of magnitude estimate, but still relatively broad, usually within -15% to +30%.
  • Conceptual Estimate: Developed during the conceptual phase, generally more accurate than preliminary estimates but less so than definitive.
  • Definitive Estimate: Based on detailed project information, this is the most accurate form of estimate, often within -5% to +10%.

Analysis and Detail

  1. Order of Magnitude: Useful for gauging feasibility but not reliable for budgeting.
  2. Preliminary: Better for assessing financial viability but still subject to significant change.
  3. Conceptual: Provides a general idea of costs but lacks the precision needed for actual budgeting.
  4. Definitive: Considered the most accurate as it is based on comprehensive details including drawings, specification, and various constraints.

Verify and Summarize

In summary, the definitive estimate is the most precise form of project cost estimate, suitable for final budgeting and financial planning.

Final Answer

Definitive is the most accurate type of project cost estimate.

This problem has been solved

Similar Questions

These are part of the Techniques for Estimating Project Costs, except:*A. Three-Point EstimationB. Analogous EstimationC. Direct Labor Expense

Which of the following is not a method of creating a project budget?Top-down budgetingComparison budgetingActual budgetingRoll-up budgeting

The cost baseline is developed during which process?Develop scheduleDetermine budgetEstimate costsMonitor & control project work

Which of the following are cost estimating methods recommended by NRM1? Cost per m2 Work package Functional unit Elemental cost planning Elemental

As a firm begins to operate outside the relevant range, the accuracy of cost estimates for fixed and variable costs:

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.