Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive
Question
Solution 1
Break Down the Problem
- Identify the types of project cost estimates.
- Determine the accuracy of each type.
Relevant Concepts
- Order of Magnitude Estimate: Typically used in the early stages of a project, these estimates can vary greatly, usually within a range of -25% to +75%.
-
- Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI
Similar Questions
These are part of the Techniques for Estimating Project Costs, except:*A. Three-Point EstimationB. Analogous EstimationC. Direct Labor Expense
Which of the following is not a method of creating a project budget?Top-down budgetingComparison budgetingActual budgetingRoll-up budgeting
The cost baseline is developed during which process?Develop scheduleDetermine budgetEstimate costsMonitor & control project work
Which of the following are cost estimating methods recommended by NRM1? Cost per m2 Work package Functional unit Elemental cost planning Elemental
As a firm begins to operate outside the relevant range, the accuracy of cost estimates for fixed and variable costs: