3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?9101112

Question

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?9101112
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

First, let's find out how many hours in total it takes for 3 pumps to empty the tank.

3 pumps can empty the tank in 2 days working 8 hours a day. So, the total hours it takes for 3 pumps to empty the tank is 2 days * 8 hours/day = 16 hours.

Since 3 pumps take 16 hours to empty the tank, 1 pump wo Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?9101112

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day

12 girls can do a a piece of work in 30 days, working 8 hours a day . In how many days 18 girls can do the same piece of work while working 4 hours a day?

45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day

1/3