Which of the following are cost estimating methods recommended by NRM1? Cost per m2 Work package Functional unit Elemental cost planning Elemental
Question
Which of the following are cost estimating methods recommended by NRM1?
- Cost per m2
- Work package
- Functional unit
- Elemental cost planning
- Elemental
Solution
The cost estimating methods recommended by NRM1 (New Rules of Measurement) are:
-
Cost per m2: This method estimates the cost based on the total area of the project. It's a simple and quick method, but it may not be very accurate as it doesn't take into account the complexity or quality of the project.
-
Work package: This method breaks down the project into smaller, manageable parts or "work packages". Each package is estimated separately, and then all the estimates are added together to get the total cost. This method is more accurate than the cost per m2 method, but it requires more time and effort.
-
Functional unit: This method estimates the cost based on the function of the project. For example, in a hospital project, the cost could be estimated per bed. This method is useful for projects where the function is more important than the size.
-
Elemental cost planning: This method breaks down the project into its elements (like walls, floors, roofs, etc.) and estimates the cost of each element. This method is very detailed and accurate, but it requires a lot of time and effort.
-
Elemental: This method is similar to the elemental cost planning method, but it's less detailed. It estimates the cost of each element, but it doesn't break down the elements into smaller parts. This method is quicker than the elemental cost planning method, but it may not be as accurate.
Similar Questions
These are part of the Techniques for Estimating Project Costs, except:*A. Three-Point EstimationB. Analogous EstimationC. Direct Labor Expense
Expenditures for acquisition of raw materials for your products are a part of which Costing type?1 puntoDirect CostIndirect CostStaff CostMaterial Cost
Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive
COST-BENEFIT ANALYSIS IS PERFORMED DURINGQuestion 10Answera.Maintenance b.Feasibility study phasec.Implementation phased.Analysis phase
Describe the main steps of prcject cost management process. Clearly state the input andoutput of each step of the cost management proces s. (6 Marla)