A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?

Question

A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To solve this problem, we first need to understand that the rate at which A and B can complete the work together is the sum of their individual rates.

Step 1: Find the rate of A and B working together. Since they can complete the work in 35 days, their combined rate is 1/35 work per day.

Step 2: F Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?

A and B can do a piece of work in 20 days, B and C can do it in 60 days. If B alone can do it in 90 days, in how many days will A and C do it together?

A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How manydays would B alone take to do the same work?

A is twice as good a workman as B and together they finish a piece of work in 14 days. A alone can finish the work in:

If A can do a piece of work in 10 days and B can do the same work in 15 days, how long will they take to complete it together?

1/3