PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options

Question

PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

The correct answer is a. Optimizing. PERT (Program Evaluation Review Technique) is a planning and control tool used for defining and controlling the tasks necessary to complete a project. It is suitable for optimizing project schedules as it helps in identifying the minimum time needed to complete a Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options

Critical path method is suitable for _____________ project schedulesa.Optimizingb.Minimisingc.Maximizationd.None of the given options

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752

Given the CPM/PERT project network segment above, the latest start (LS) activity 3 isGroup of answer choices8572

1/3