PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur
Question
Solution 1
The correct answer is a. Non-repetitive nature. PERT (Program Evaluation Review Technique) is a planning and control tool used for defining and controlling the tasks necessary to complete a project. It is particularly useful for projects where the time required to complete various tasks is unknown a Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv
Similar Questions
PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur
These tools relieve the systems analysts of many repetitive tasks, develop clear documentation, and, for larger projects, coordinate team member activities.
PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time
Use the formula for continuously compounded interest, A = Pert, to find the annual interest rate for an $8000 investment that earns $410.17 in one year.
PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration