PERT is useful when we have the following time duration except:

  • a. Optimistic time
  • b. Pessimistic time
  • c. Most likely time
  • d. Certain Duration
🧐 Not the exact question you are looking for?Go ask a question

Solution

The PERT (Program Evaluation and Review Technique) is a statistical tool used in project management, which is designed to analyze and represent the tasks involved in completing a given project. It incorporates uncertainty by making it possible to schedule a project while not knowing precisely the details and durations of all the activities.

The time estimates in PERT include:

a. Optimistic time: the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.

b. Pessimistic time: the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).

c. Most likely time: the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.

The option that PERT does not use is:

d. Certain Duration: PERT is designed to handle uncertainty in activity completion times. Therefore, it does not use a certain duration as it assumes there is always some degree of uncertainty in how long each task will take.

This problem has been solved

Similar Questions

PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration

PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752

Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 is

PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.