PERT is a three time estimate and gives more weightage to
Question
- a. Optimistic time
- b. Most likely time
- c. Pessimistic time
- d. Expected time
Solution
The PERT (Program Evaluation and Review Technique) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. It involves three time estimates:
- Optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
- Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
- Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
The expected time (T) for each activity is calculated using the formula:
T = (O + 4M + P) / 6
So, PERT gives more weightage to the Most Likely Time (M).
Similar Questions
PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration
Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates
PERT is used for one time projects that involve activities of_________a.Non-repetitive natureb.Repetitive naturec.Continuous natured.Invalid in natur
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752
PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.