CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time

Question

CPM model will be used only when the duration of the activities are________ .

a. Certain
b. Uncertain
c. Optimistic time
d. Pessimistic time

🧐 Not the exact question you are looking for?Go ask a question

Solution

The Critical Path Method (CPM) is a project management technique used to determine the longest sequence of dependent tasks that are crucial for the completion of a project. It is important to understand when to apply this method effectively.

  1. Certain Duration: CPM is ideal when the duration of project activities can be precisely estimated. This is because CPM relies on fixed time estimates for the various tasks involved in a project. It calculates the earliest and latest that each activity can start and finish without delaying the project.

  2. Uncertain Duration: For activities with uncertain durations, it is more appropriate to use the Program Evaluation and Review Technique (PERT), which incorporates variability in activity duration through statistical methods.

  3. Optimistic or Pessimistic Time: These terms refer to extreme scenarios of activity durations (best case and worst case), which again suggest variability that CPM does not handle well.

Final Answer

The CPM model will be used only when the duration of the activities are a. Certain.

This problem has been solved

Similar Questions

The latest possible time an activity can start without delaying the projecta.Latest start timeb.Latest finish timec.Project Costd.Duration

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration

What is a particular task/exercise in a project known as CPM?a.Activityb.Eventc.Taild.Head

Which of the following is not a typical time management technique? Prioritising Procrastination Time management Establishing SMART goals

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.