CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time
Question
Solution 1
The CPM model will be used only when the duration of the activities are certain. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Kno
AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem. Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob
Similar Questions
CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time
Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse
PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse