The higher the node number, the longer the activity will take.Group startsTrue or False
Question
Solution 1
False. The node number in a project management context, often used in techniques like the Critical Path Method (CPM), does not determine the duration of an activity. The node number is just a way to identify and organize the activities. The duration of each activity is determined by factors like the Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv
Similar Questions
The higher the node number, the longer the activity will take.Group startsTrue or False
If the water potential in an environment is higher, water will flow into that environment.Group startsTrue or False
Leaders tend to have higher extraversion scores than nonleaders.Group startsTrue or False
Other things being equal, the higher the debt to equity ratio, the higher the risk of bankruptcy.Group startsTrue or False
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False