In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse

Question

In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

True

In the time-cost CPM (Critical Path Method) model, it is generally assumed that cost is a linear function of time. This means that as more time is spent on a task, the cost of that task increases proportionally. This assumption is used to simplify the process of determining the optimal project Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study prob

Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solve study problem.
Knowee AI StudyGPT is a powerful AI-powered study tool designed to help you to solv

This problem has been solved

Similar Questions

In the time-cost CPM model, cost is assumed to be a linear function of time. Group of answer choicesTrueFalse

Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse

In the Random Access Machine (RAM) model, which operation is NOT assumed to take constant time?Group of answer choices

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

CPM model will be used only when the duration of the activities are________ .a.Certainb.Uncertainc.Optimistic timed.Pessimistic time